Paswara Papers is planning to expand its paper mill in Mohiuddinpur in Uttar Pradesh. The project will be developed in two phases with a total capacity of 140,000 TPA. In first phase, a capacity of 40,000 tpa will be set up with an investment of ₹ 300 million.
In the second phase, the remaining 100,000 TPA of capacity for high RCT kraft paper will be commissioned. The project is likely to operational by 2020. The company has signed up an agreement with the state government under Uttar Pradesh Udhyog Nivesh Nidhi.
Project Location | Mohiuddinpur,Uttar Pradesh |
Project Cost (in million) | ₹300 |
Project Capacity | 40000 tpa |
Project Status | Implementation |
Commissioning Date |